Meeting Date:
|
9/28/2017 - 7:00 PM
|
Category:
|
New Business and Reports to the Board
|
Type:
|
Info
|
Subject:
|
Capital Projects--Contract Approval Process
|
ACPS 2025 Strategic Plan Goal:
|
Objective 4.1 Optimal Learning Environments and Infrastructure In collaboration with City partners, ACPS will move aggressively to modernize all learning environments, expand or otherwise adapt facilities to meet projected changes in school enrollment, and ensure equitable application of capital improvements throughout the school division.
|
Funding Source or Fiscal Impact (where applicable)
|
|
File Attachment:
|
|
Agenda Item Summary:
|
This is a presentation for the School Board to review lessons learned and potential improvements in CIP project execution.
|
Background:
|
Over the summer prior to school year 2017-2018, ACPS completed or achieved major milestones on several major CIP projects including West End Elementary School, Patrick Henry Pre-K – 8 School, Relocatables at T.C. Williams High School: King Street Campus and at James K. Polk Elementary School. Challenges experienced in achieving these major milestones offer several insights on how to significantly improve major CIP project execution in the future.
|
Recommendation:
|
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Mike Herbstman - Chief Financial Officer
|
|
Signed By:
|
|
Richard Jackson - Interim Director of Educational Facilities
|
|
Signed By:
|
|
Lois Berlin -
|
|
|
|
|
|
|
|