Subject: High School Project Update: Cost Estimates and Site Discussion
ACPS 2025 Strategic Plan Goal:
Objective 4.1 Optimal Learning Environments and Infrastructure
In collaboration with City partners, ACPS will move aggressively to modernize all learning environments, expand or otherwise adapt facilities to meet projected changes in school enrollment, and ensure equitable application of capital improvements throughout the school division.
Policy: FA - Facilities Development
Funding Source or Fiscal Impact (where applicable)
File Attachment:
181220_MEMO_High_School_Project_Update.pdf
181220_PRESENTATION_Update_HS_Project_v2.pdf
Agenda Item Summary: At the December 6th regularly scheduled School Board meeting, additional information regarding potential cost implications was requested. Staff has conducted additional analyses although the process is very early. The information in this update represents preliminary information regarding capital and operating costs considerations and site implications.

The project team is working with the Curriculum and Instruction Department to develop coordination parameters for the program design and upcoming project-specific educational specification efforts as planning continues. Staff is also working with its consultants to ensure all requirements of this critical project are being met and will updated the School Board on next steps.
Background: Our total high school enrollment currently exceeds the TC Williams design capacity by with expected growth projected to continue. The School Board allocated $100,000 in the FY 2018 Capital Improvement Program (CIP) budget to engage the community on solutions for needed high school capacity. In the following FY2019 fiscal year, with the Ad-Hoc Joint City-Schools Facilities Investment Task Force acknowledgement, the City included $5.15M to initiate immediate planning efforts and to begin design.

Work began in earnest in July 2018. During the November 8, 2018 board meeting and the November 26, 2018 work session, ACPS staff and project consultants Stantec Architecture and Fielding Nair International (FNI), Inc., presented the first two phases of the planning work including: Discover – research of related national high school models and future workforce studies that align with the feedback and objectives related to ACPS, and Engage – an emerging educational vision based upon an online survey with 421 responses, over 40 in person meetings, including 22 student class discussions, 4 town hall work sessions, 2 business/community leader focus groups and TC Williams staff meetings. The Educational Vision includes the following pillars: Community Connected; Diversity as a Strength; Experiential Learning.

The research models and proposed educational vision resulted in the consultant’s recommendation that ACPS adopt a ‘connected high school network concept’ or multiple campuses for meeting the expansion needs of Alexandria’s high school of the future.
The Board determined that time for additional understanding of the recommendations, comparative cost models and more staff and community engagement was needed. The Board also adjusted the vote to January 24th to allow the newly elected Board Members to participate in this milestone decision.
Recommendation: The Superintendent recommends that the School Board continue to review the recommendation materials.